Cable Testing / Termination & OHL Testing

Cable Testing / Termination & OHL Testing

Dubai Metro – RTA (2009 – 2010)

AMEC’s skilled team carried out the cable termination and testing of 11kV and 33kV cables for the entire run of Red Line, Green Line and Airport Mover projects of Dubai Metro.

FIATAVIOMirfa, Abu Dhabi

AMEC was awarded the testing of 1C x 33kV cables at Mirfa Power Station.

BABCOCK , Abu Dhabi

AMEC was awarded the testing of 1Cx33KV & 3Cx11 KV cables at Mina Power Station & Al Ain Power Station.

ADDC, Various, Abu Dhabi

AMEC was responsible for testing of cables using VLF AC Hipot on 11kV & 33kV both 1C and 3C cables for ADDC at various stations in Madinat Zayed, Gayathi, Ruwais, Mussaffah, EMAL – Taweelah, Sadiyat Island, Yas Island and many more.

Our testing team carried out overhead line testing of 132/220/400kV for SEWA, DEWA, FEWA and TRANSCO at various locations in UAE.